The Arad South Terminal is approaching inauguration

The construction of the terminal is nearing completion, and it will start operating by the end of 2020.

Soon, containers, goods and grain will leave here every day for important railway junctions in Western and Southern Europe, or even the Orient, that’s why our team works diligently to get all the details up and running.

Until this phase, the installation and testing of the 4 unloading lines, the pouring of the concrete platform and the installation of the temporary offices for transport operators have been completed. In parallel, we are developing the information infrastructure, we are hiring staff and conducting detailed constructions – fencing the terminal, signaling works and installation of access barriers.

 